Here's the proposed time-line and the actual dates: start & finish:

PLANNED TIMING
 
Layout and dig the hole:        o         August 28
Install steel re-bar:           o         September 5
Dig & install piping:           o         September 10
Inspection by the City:         o         good luck !
Gunite the pool:                o         September 20
Install tile & coping:          o         September 24
Decking:                        o         September 30
Plaster:                        o         October 5
Fill Her Up:                    o         October 18
Swim Hot-Tub & Fire Pit:        o         October 21
========================
Total Time::                         45 days
 

ACTUAL MILESTONES HIT
 
Layout and dig the hole:        o         August 28
Install steel re-bar:           o         September 6
Dig & install piping:           o         September 11
Inspection by the City:         o         September 12
Gunite the pool:                o         September 17
Install tile & coping:          o         September 30
Decking:                        o         October 17
Plaster:                        o         December 12
Fill Her Up:                    o         December 12
Swim Hot-Tub & Fire Pit:        o         December 23
========================
Total Time::                        102 days